Two foreign mining groups, a dozen years apart, have signed deals to move ore from the same proposed mine in northern Mauritania. Both went to the same company for transport: SNIM, the state miner that owns and runs the railway to the Atlantic. The latest agreement, signed with Essar on 2 November, tells us more about where Mauritania has leverage than the reported US talks on exploration and geological mapping. Essar needs a way to move millions of tonnes of ore. SNIM can offer one without giving up the tracks.

That gives the Mauritanian company a choice it wouldn’t have if a foreign mine ran its own railway: it can carry another producer’s ore as well as its own. The government expects transport income and shared maintenance costs. But the published account doesn’t disclose the tariff, the tonnage Essar has committed to move, or whether it had another viable route. The deal shows who can grant access to this line, not how much that access was worth at the negotiating table.

The strongest evidence for the railway’s value is also the clearest warning against overstating it. In 2014, SNIM agreed to carry ore from the same Askaf mine for Glencore, store it at the coast and ship it through the ore port. The mine was never built. Two developers choosing the same corridor is better evidence of its commercial appeal than any claim that they had no alternative. Yet the first deal shows that a railway owner can offer a route to market and still be left without a customer.

Outside money gives SNIM another way to use the line. Last year the European Investment Bank and African Development Bank signed $275 million in loans directly to SNIM. The loans are for upgrading the railway and connecting two other mines, not financing Essar’s. At one of them, El Aouj, SNIM owns 92% of the project company and plans to fund 40% of development from its own resources. The company can build up its own mining business while selling transport to someone else’s. It still needs other capital to do so; signed railway loans are not cash already spent, nor do they finance the mine itself.

Glencore and Essar chose the same route for the same deposit. That gives SNIM a service it can sell without surrendering the railway. But Glencore had a route to the port and Askaf never entered production. Essar now has a route under contract, not a mine in operation.