When Nigeria cut electricity exports to Niger after the 2023 coup, it took away a source that had supplied 71% of the country’s electricity consumption. Niger’s national utility ran its existing thermal plants harder, drawing on fuel from the country’s own refinery. A new solar plant helped. The World Bank’s review found that blackouts and rationing eased, but the fallback cost more than imported power. With tariffs unchanged, the extra cost fell on the utility. Niger paused new connections that year.
A West African electricity market could give Niger a better option than burning more fuel. The November construction update shows why that option is still limited: new equipment is already helping existing import lines, but a section of the planned connection from Benin is still being built. The 2023 cutoff exposed the problem that cheaper deals alone cannot fix: the power has to reach the part of the country that lost it.
In July, Niger’s energy minister said domestic generation in the western zone, which includes Niamey, could cover about 86% of its recorded peak demand without imports. In the centre-east, which includes the cities of Maradi and Zinder, domestic supply could cover only 38%. These are July capacity comparisons, not predictions of how long the lights would stay on. The decisive point is that the two zones are not connected inside Niger: spare power in one cannot simply make up a shortage in the other.
The equipment, operating since July, helps stabilise both existing lines from Nigeria; it does not supply electricity if Nigeria stops sending it. The new branch from Benin would enter at Zabori, on Niger’s western grid. The river crossing near Benin’s border town of Malanville was still under construction in November. Once usable, that connection could give the west another supplier. It would not give Maradi or Zinder a backup without a separate domestic link from Zabori to the centre-east.
The regional power pool expects next-day trading to begin in early 2027. Such trade can be worth having even without a crisis: the World Bank credits imports of Guinean hydropower with helping halve the cost of generating electricity for Guinea-Bissau’s utility. But buying cheaper power is easier than securing a dependable replacement. For a supplier outage, another seller must have power to spare, a route that can deliver it and confidence it will be paid. A political embargo could block a sale even if all three are in place.
For a mill in Maradi, that difference could determine whether it can keep grinding when imports stop or has to wait for local power to come back. During the 2023 cutoff, running Niger’s own plants harder eased rationing. A second source that can actually reach the centre-east would give users there an alternative to taking turns with the power still available.